Announcements on Improvement Projects
Daily construction reports for the E. Lyon Street Improvements Project. These daily
reports highlight work completed from 4/22/25 to 4/28/25.
Completed work:
- Inlet protection products have been installed on inlets within the Phase 3 project
area.
- Asphalt milling has been completed for Phase 3 of the project, including E. Lyon
Street from the eastern project limits to Grant Street intersection (milling stopped
just east of the intersection) and Wilson Street. Duininck hauled millings to the
salvage lot north of the City.
- Sawing has occurred for all Phase 3 pavement removals. Driveways have been removed
from properties on the 600 block of E. Lyon Street. Portions of concrete curb and
gutter have been removed from the southern end of Wilson Circle.
- Duininck completed storm and sanitary sewer near the city maintenance shop. During
this activity, the Contractor removed the shop’s septic tanks and hooked services
up to the newly installed sanitary sewer. The only remaining work in this area is
a drain line connection from the property to the West to the new storm line.
- Duininck recompleted the replacement of the 16” plug valve at Control Structure #4.
Upcoming work:
- A water shutdown occurred today to cut and cap the existing water main in three locations
near the intersection of Eisenhower and E. Lyon Street. Doing so will allow for the
Contractor to restore water to residents while other utilities are installed. One
temporary service had to be installed to 607 E. Lyon Street to maintain water to
the property.
- After abandoning the water main in the intersection, the Contractor plans to begin
installing water and sanitary sewer on E. Lyon Street, starting at the east project
edge and working west. During this time, portions of E. Lyon Street and its intersections
within the project area will be inaccessible. Open trenches will be backfilled as
work progresses, areas of work will be reopened to access once backfilled and compacted.
- Duininck plans to have another crew on-site later this week to work on the Control
Structure #1 bypass line and splitter structure.
DAILY FIELD OBSERVATION REPORT through November 11, 2024
Updates as of November 1, 2024:
1) All hydrants done
2) Grant street sewer work is completed
3) Paving begins on Jackson/Washington and trail in vicinity of School
4) Sanitary sewer project near City Shop begins in next week
Fire Hydrant Replacement Status
(GREEN = Hydrant replaced, grass seeding may still be in progress on some)
(RED = TO BE SCHEDULED)
Click Here for Letter to Residents for information on Fire Hydrant Replacement
- Hydrant #1: COMPLETED
- Hydrant #2 Industrial Park: COMPLETED
- Hydrant #3 Industrial Park: COMPLETED
- Hydrant #4 Industrial Park: COMPLETED
- Hydrant #5 VANS TRAILER PARK: COMPLETED
- Hydrant #6 Madison and 2nd Street: COMPLETED
- Hydrant #7 Madison and 4th Street: COMPLETED
- Hydrant #8 Madison and 5th Street: COMPLETED
- Hydrant #9 7th Street (north side): COMPLETED
- Hydrant #10 Washington and 5th Street: COMPLETED
- Hydrant # 11 4th Street (going out of town): COMPLETED
- Hydrant # 12 Washington and 3rd Street: COMPLETED
- Hydrant # 13 Washington and 2nd Street: COMPLETED
Lyon Street Project
- Construction in the vicinity of 6th street and Grant is scheduled for to start on
14 Oct and is scheduled to conclude by end of Oct 2024. This time period will restrict
traffic flow; IMPACT: The upgrade of this sewer line will facilitate gravity flow
and integration of Lyon street sewer to Grant Lift station
- Next Lyon Street Improvement project meeting is 21 Oct, 1 PM at City Community Center
General Guidance
- Construction work will only be on Mondays to Fridays, from 7AM to 7PM
- If you are mobility challenged resident on Lyon street or require any special assistance
please contact Chesney Gutter, Acting City Administrator 507-872-6144
- Tree Trimming on E. Lyon Street is scheduled for late October, trees will be marked
by Keck Tree Service will be cut down to 1 foot
These daily reports highlight work completed from 05/05/25 to 05/09/25.
Completed work:
- Remaining City Wastewater Treatment Facility work has been completed. The Contractor
replaced all plug valves, installed bypass piping near Control Structure #1, and
set the new splitter structure with riser pipes.
- Water main installation is complete to approximate STA 26+35. This segment has passed
pressure and bacteriological testing requirements.
- Sanitary sewer installation is complete on E. Lyon Street through the Wilson Street
Intersection.
Upcoming work:
- Duininck plans to connect newly installed water main to the existing water main near
the intersection of Eisenhower Street and E. Lyon Street.
- Storm sewer installation is to occur through the 600 block of E. Lyon Street.
- Following storm sewer install, the crew plans to install permanent water and sewer
services on the 600 block of E. Lyon Street.
- Another Duininck crew will continue to install water and sewer main lines to the
South on Wilson Street.
Daily construction reports for the E. Lyon Street Improvements Project. These daily
reports highlight work completed from 4/29/25 to 5/2/25.
Completed work:
- Water main near the intersection of Eisenhower and E. Lyon Street was successfully
cut and capped.
- Water main and sanitary sewer main installation is complete in the greenspace to
the East of 607 E. Lyon Street (approximate STA. 95+80 to STA 96+95).
- Sanitary sewer main on E. Lyon Street is installed to approximate STA 26+90. During
sanitary sewer install, Duininck installed SMH #6, #7, and #8.
- Bypass piping at Control Structure #1 at the City’s wastewater treatment facility
is completed and functional.
- The 16” Plug Valve located in Control Structure #3 feeding Primary Pond #2 has been
replaced. Duininck has replaced a total of 2 plug valves, with the other located
in Control Structure #4.
Upcoming work:
- Duininck plans to return to the intersection of Eisenhower and E. Lyon Street tom
complete water main installation in the area. The Contractor intends on installing
water to catch up to the installed sanitary sewer progress. Once caught up, the Contractor
will continue West with sanitary sewer and water main installation to just east of
the intersection of Wilson Street and E. Lyon Street. Duininck has indicated that
once water and sewer main are to Wilson Street, they will return to the eastern project
limits to install storm sewer.
- The new splitter structure is to be set this week with the extra crew the Contractor
has on-site.
- Duininck plans to complete the replacement of the remaining 16” plug valves and supports
this week.